This operation updates details about a scheduled integration instance by ID. The integration can be scheduled to run once or at a recurring frequency.
The associated Access Control Point is SCHEDULE_INTEGRATIONS.
Frequency Type | Frequency | Interval |
1 (Once) This frequency type is used to schedule an integration that will be executed only once on provided future date time. | Not Applicable | Not Applicable |
2 (Daily) This frequency type is used to schedule an integration to execute daily. | Not Applicable | Any valid numeric number. The number of days to skip between runs. |
3 (Weekly) This frequency type is used to schedule integration to execute weekly | Days of week on which to run the schedule 1 (Sunday) 2 (Monday) 3 (Tuesday) 4 (Wednesday) 5 (Thursday) 6 (Friday) 7 (Saturday) | Any valid numeric number. The number of weeks to skip between runs. |
4 (Monthly) This frequency type is used to schedule integration request to execute monthly. | Months on which to run the schedule: 0 (January) 1 (February) 2 (March) 3 (April) 4 (May) 5 (June) 6 (July) 7 (August) 8 (September) 9 (October) 10 (November) 11 (December) | 1 to 31 (January, March, May, July, August, October, December) 1 to 28 (February - Non Leap Year) 1 to 29 (February - Leap Year) 1 to 30 (April, June, September, November)
|
5 (Hourly) This frequency type is used to schedule integration request to execute hourly. | Not Applicable | Not Applicable |